Hi All,

I have a Material in Plant 1, with Valuation Category H.

I want to extend this material to Plant 2 with Valuation Category 'X' (Auto Batch)

Its not accepting X, any other entry would be possible

It says "With Single batch valuation, batch management must be defined. The following plants have no batch management requirement: Plant 1"

If i activate batch management in Plant 2, it is working.....but i dont want Batch management for this material.

How do i solve this.

Pls help.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

First you extend the material to another plant. Then In MM02 remove the batch manangement and In MSC2 also deflag the batch activation.

Regards,

Andra

Former Member
0 Kudos

Hi,

We can not remove Batch management thru MM02, once it is set in MM01. Its a gray field.