How I can change the Plan Date and the Call Date on IP10?

Former Member
0 Kudos

I need to change the Plan Date and the Call Date on IP10 because the Plan Date is not the same as the last reference date (TECO). We changed the maintenance plan parameters and the system created 2 orders. Now we changed the maintenance plan parameters including "Completion requirement" and closed both orders order the system don't create the next order because it have a Schedule Hold with a date. Now we don't have the next order created and the call date for the next order is 1 years in the future and we need the order create 6 months in the future. We are talking about 2000 maintenance plan with this situation. What we can do to resolve this?

Accepted Solutions (0)

Answers (2)

Answers (2)

sundar_desai2
Active Contributor

Hi,

Plan date and call dates are calculated automatically based on cycle and start date provided for maintenance plan. Kindly restart or start in cycle the plan with new start date for getting new plan and call dates.

e.g. for single cycle: Provide start date for plan as of last maintenance completion date.

e.g. for strategy based plan: Provide the start date of plan as of last maintenance completion date and select the respective due package from start in cycle.

Regards,

Sundar

akharisma
Explorer
0 Kudos

Hi Davila.

Use IP19 for change the plan date, but it just work for single cycle plan.

Regards,
Agung Kharisma