Capacity Planning Fields - CM01

Former Member
0 Kudos

Hi guys,

I need help on getting some information from SAP.

I have a request for a report that need the Availability Capacity for Machines.

This information can be found in T-Code CM01.

See below the result of the transaction:

Week Requirements AvailCap. CapLoad RemAvailCap Unit

23.2009 0.00 67.86 0 % 67.86 H

24.2009 0.00 105.30 0 % 105.30 H

25.2009 0.00 105.30 0 % 105.30 H

26.2009 0.00 105.30 0 % 105.30 H

27.2009 0.00 105.30 0 % 105.30 H

28.2009 0.00 105.30 0 % 105.30 H

29.2009 0.00 105.30 0 % 105.30 H

30.2009 0.00 105.30 0 % 105.30 H

31.2009 0.00 105.30 0 % 105.30 H

Total >>> 0.00 910.26 0 % 910.26 H

The field I need is the one that says AvailCap.

I have debuged the program lots of times... have found a bunch of function modules but can't figure out how this is calculated.

Can any one help? Pleeeeeeeeeeeease!

Have any of you used this before?

Thanks a lot and regards,

Fernanda

Accepted Solutions (1)

Accepted Solutions (1)

former_member184627
Active Contributor
0 Kudos

Hi,

The available capacity can be find from the work center.

In CR03 transaction enter the work center & plant. Goto the capacity tab page & click the capacity header (displayed in the bottom). Now click intervals & shift button.

Now check the valid from & To dates & then select the required date range & see the value displayed in the capacity column. For Eg: if for a day the working hours is 8 Hr & capacity utitlisation is 100 % & Number of individual capcity is 1, then the avaialable capacity is 8 hours per day & for a week of 5 working day the available capacity will be 40 hours.

In number of individual capacity is 2 then the available capacity will be 80 Hrs.

Regards,

Senthilkumar