Hi,
I having subcontract material u201CXu201D,
I made BOM for material u201CXu201D of child material u201CAu201D & u201CBu201D
I want to give material u201CXu201D to subcontract to vendor u201CZu201D
As per the process after making subcontract po to vendor u201CZu201D for material u201CXu201D, We have to send material u201CAu201D & u201CBu201D to vendor u201CZu201D.
We want to combine the functionality of the subcontract process and combine it with the BOM from a work order.
There a way to buy an item from Subcontract which consist of material u201CAu201D &u201DBu201D, in same subcontract po.
When we receive the finished kit, then, in the BOM from the work order on the shop floor, they are not able to see the sub-component of the kit. This is what we want?
(buying subcontract material and giving subcontract for finished goods to same vendor in single po , whether this possible ?, if yes how ?)
please help
Thanks in advance
Prashanth
Edited by: prashanth.venkategowda on Jun 4, 2009 7:25 PM