Hi All,
I want to calculate duration ( Setting calculation Key =1 ) based on the setting of workcenter & after giving the work .
Ex :I have a work center (Excavation Machine) which excavate 80M3 sand in 24 hours & same time i had created an activity which have the work of 8000 M3. Now I want to calculate the duration of activity by the setting of calculation key ie calculate duration.
pl help me that what formula i need to maintainin work center for calculating the duration automatically.
Refgards,
Deependra