on 06-04-2009 12:37 PM
Dear Experts,
my client scenario is like creates the sales order from sales order project will create automatically next MRP -
PR--
please explain me clearly which department each activity done and how postings will happened.
Regards
etr
cloded
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In PS Department each WBS ( Like Procurement, Assembly, Detailed engineering, Civil engineering ) handled by different end users ?
regards
etr
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
PR will crete through the Nework Order ---> Network Activity --> Release Network Activity all will execute by PS department.
PR release-> PO -
WIP of the WBS element will calculated by PS depatment
Dispatch activities will handled by MM and SD depatment.
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.