Jun 04, 2009 at 08:31 AM

Lock Posting for particular WBS Element

1989 Views

Dear Friends,

I belong to SAP SD & I am new to PS module.

My client requirement is to lock posting to a particular WBS element of a Project once say 90% of the planned Cost is reached.

To explain the above in detail - say we have planned Rs. 1,00,000 as Planned Cost for a particular WBS element of a Project & if we have already posted Actual cost of Rs. 90,000 for that particular WBS element, then system not allow further posting (by way of GRN / MIRO or JV), unless a senior releases the block.

Our Business flow is - Ceate Project, create WBS elements for the Project, then plan Cost & Revenue for the each WBS element of a Project & then carry out business transactions like GRN, JV (expences posting), etc with reference to WBS elements.

Please let me know how to achieve the above requirement.

Thanks,

Jignesh Mehta

Mumbai.