Former Member
0 Kudos

i am working on slow/nonmoving items and using mc46 report. i use this report to check last consumption date and when i check with mb51. it does not match.

kindly suggest correct or other way

regards

Accepted Solutions (0)

Answers (6)

Answers (6)

Former Member
0 Kudos

Hi,

This is a report to check the material is not moved the certain period for consumption ,

If u give the 360 days in consumption field , then you run the system search and give material is not moved from store to consumtption for one year.

But its not match the MB51, it is only for material documents.

Regards,

Andra

Former Member
0 Kudos

is consumption of material with special stock considered in mc46 or not.

actually we have two type of stocks one for o&m other for project. what i am observing its giving last consumption data on o&m issues not for project material with q type.

regards

former_member433442
Active Contributor
0 Kudos

Hi,

Use S033 table and you can get the required report.

Regards,

Prabu

Former Member
0 Kudos

Run the report with below parameters

Plant (Enter all plants in which the materials exist or tick All plants cumulated)

Material nos.

Period :

And the below check boxes ticked -

- Daily usage check box

- Materials with zero stock

- Materials marked for deletion

- Including MRP consumption

- Stock value

Check & revert.

Former Member
0 Kudos

What level u look report like PLant etc, based on that it is normally correct or check at global level..i.e.at top of screen tick & see.

regards,

NNK

Former Member
0 Kudos

Hi ,

MC46 is a aging report used to identify the materials which are Obsolute.

If you tick the "No. of days up to last consumption", system will try to search the materials for which no movement has been happened for the given no .

of days.

And the next two radio buttons will give the Top or Bottom materials in the list .