on 06-04-2009 9:06 AM
I find certain settings in the controlling area settings - settings for each fiscal year for planning and price calculation. My requirement is to calculate the actual price of the activities. What should be my settings in this area in order to calculate the actual price of my activities ?
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In Maintain Version in settings for Controlling folder in Settings for each Fiscal Year under Price calculation tab
Select 1 Revaluation in separate transaction (or) 2 Revaluation in original transaction for Revaluation at Actual Prices field. Details as bellow
Revaluation at Actual Prices
Indicator determining whether actual activities in a version are
valuated with actual prices and how the valuation is performed.
0 Not valuated
All actual activities valuated with the plan price
1 Revaluation in separate transaction
All actual activities valuated with the actual price; original
allocation unchanged
The differences between allocations valuated with plan and actual
prices are posted under a separate transaction (actual price
calculation).
2 Revaluation in original transaction
All actual activities revaluated with the actual price; original allocation changed
The differences between allocations valuated with actual and plan
prices are not shown with this option.
Edited by: Bhagiradha Pinnamareddy on Jun 4, 2009 2:35 PM
Edited by: Bhagiradha Pinnamareddy on Jun 4, 2009 2:36 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Purely Iterative Price
Indicator controlling whether parallel prices are calculated and stored for activity types as part of the price calculation. You can calculate prices separately for each version/fiscal year.
Indicator active
o Activate the indicator only if you set allocation prices manually during activity type planning. If the indicator is active, price calculation gives a purely iterative price as well as the price resulting from planning (a mixture of iterative and manually-set prices). The system calculates purely iterative prices as if no manually-set prices exist, meaning that it determines separate purely iterative prices for all activity types on all cost centers in this version. Because both prices are stored in parallel, you can use the price report to compare the purely iterative prices with the prices resulting from planning. The iterative price shows the effect of manual prices on activity prices overall.
To evaluate the allocated actual activity quantities, the system uses the prices resulting from planning, provided you have not revalued the actual activities with actual prices. The purely iterative price
is essential for valuating actual activity quantities.
Indicator inactive
If the indicator is inactive, the system does not calculate purely iterative prices