author's profile photo Former Member
Former Member

Want to maintain predefine stock of semifinished all time

Hi,

My client want to keep predefine stock of HALB material on all time.

For Ex. Stock of material is 100.

Requirement for same material is 50. While carring out planning run Stock "100" should not consider by the planning run, planned order will generated for 50 only.

Regards,

Sanjay

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 04, 2009 at 07:10 AM

    Sanjay,

    You can use the concept of safety stock, make an entry in the material master in MRP view & in the t code OPJJ, select the combination of availabilty checking group & checking rule i.e. PP, click on details.

    In the next screen, under stocks, unmark the 'safety stock' so that the value you entered in the material master won't be considered for material availabilty checking & your requireemnt can be fullfilled.

    Make sure that the the same availabilty checking group either 01 or 02 for whioch you have made the settings should be entered in the material master in MRP 3 view.

    Hope this helps you.

    SmanS

    Edited by: SAP PP Consultant on Jun 4, 2009 9:26 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 04, 2009 at 07:23 AM

    Hi,

    You need to maintain safety stock as 100 in MRP views 2 in material master.

    Make setting in OPJJ, include safety stock for Combination of Checking Group & Checking rule.

    Hope this help you.

    Check it & revert back.

    Regards,

    Raja.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 04, 2009 at 07:25 AM

    Hi,

    use safty stock field in material master mrp 2 view, make a safty stock of 100 , and exclude this stock for planning run.

    so for the new requirement system will not consider this as a available one and will create new orders.

    for more information on safety stock you can check on help.sap.com

    Hope it will help you.

    Regards

    Ritesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 04, 2009 at 07:28 AM

    You can use saftey stock method for this if you want to use minimum stock level or use stretgy 11 , not to use stock in planning.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 12, 2009 at 10:42 AM

    thanks

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.