Dear Experts
I am investigating about relationship of Routing and Chargeable Components, Non-Chargeable Components.
Is it possible that one routing has Chargeable Components and Non-Chargeable Components in its task?
Below is instance.
This routing is to manufacture laptop.
10: assemble1 Chargeable Components
20: assemble2 self-manufacture
30: quiality check self-manufacture
40: coating Non-Chargeable Components
50: packaging self-manufacture
If this is possible, please give the information about config and master setting.
Or should I divide the task like below?
To make halfway laptop
10: assemble1 Chargeable Components
To make laptop without packaging
10: assemble2 self-manufacture
20: quiality check self-manufacture
To make laptop with coating
10: coating Non-Chargeable Components
To make completely laptop
10: packaging self-manufacture
Kind regards,