Hello All,
I would like to enable a batch management feature for a finished product.
I would like to delete existing production orders and planned orders.
I deleted the component quantities in the production order and set the TECO flag.
I also enabled the deletion flag.
I removed all planned orders from MD04 and there are no forecast values.
MMBE also shows zero quantity.
However when I try to change the material using mm02 it still gives the following message:
Production orders already exist for the material
What else do I need to do?
Thanks in advance
George