Dear Experts,

I have an FG "A" which requires a,b & c as components. Further a & b are inhose produced for which BOM has been maintained. BOM of a contains x & y as its components where as BOM of b has p & q as its components.

Now when i execute the MRP run, the system is displaying only a, b & c but not displaying x,y,p & q

in planning result. The scenario is MTO. Please suggest how to get the required results.

Thanks in Advance,

Shaiz.