Availability control funds/wbs

Former Member
0 Kudos

Dear All,

For Availability control funds/WBS - an overall budget is made for a fund/WBS. How does this work for each year? Can all the budget be consumed in one year? How will the availability check take place?

Thanks and Regards

Gopa.

1 ACCEPTED SOLUTION

former_member184992
Active Contributor
0 Kudos

Hi Gopa,

If you have an overall budget the budget can be consumed in one year.

You can use the Release Budget functionality in this case and release each year only the allowed budget for that year.

For example:

Original Budget will be $500.000 (overall budget for 5 years)

Released Budget this year will be $100.000 and next year you will release more $100.000

Then you will be able to consume only the released budget not the overall amount.

I hope it helps you.

Best Regards,

Vanessa.

View solution in original post

1 REPLY 1

former_member184992
Active Contributor
0 Kudos

Hi Gopa,

If you have an overall budget the budget can be consumed in one year.

You can use the Release Budget functionality in this case and release each year only the allowed budget for that year.

For example:

Original Budget will be $500.000 (overall budget for 5 years)

Released Budget this year will be $100.000 and next year you will release more $100.000

Then you will be able to consume only the released budget not the overall amount.

I hope it helps you.

Best Regards,

Vanessa.