partail confirmation: part 2

Former Member
0 Kudos

hi all

when i am partially confirming an activity say 50%, and insering the actual start and finish dates...with forcast duration ............and saving the activity, these are getting projected on to my project planning board.

till now its ok,

now when i am going for confirmation for the same activity, its showing 100% by default.............its not showing the % which i have confirmed earlier ..................now i dont know, how much i have confirmed earlier ...............................any solution for this

where am i going wrong?

Regards

surya

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You are not doing anything wrong. Its SAP behaviour.

You can goto CN28 to see the history of confirmations done earlier.

Regards,

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Surya,

If you plan activity with capacities and duration as well, system proposes degree of processing till date also based on the previous confirmation apart from the activity confirmation type with only planned normal duration in activity.

Regards,

Hari Krishna.K

Former Member
0 Kudos

Hi Surya,

In Confirmation parameters for your Order type and plant combination, tick propose dates check box. with this, system will propose the actual start date from the actual finish date entered in the earlier confirmation (during 50 % confirmation) and actual finish date as today's date with time. this will helps you some extent to get the actual start date of next confirmation automatically. For remaining 50% progress to be updated automatically during next confirmation by system, i dont think system will propose automatically.

regards,

Hari.