Open PS

54 Views

Hello,

My client is using SAP PS for project execution and doing scheduling in SAP.

When he is downloading data from SAP ECC to MS office project using open PS functionality and interface , dates are getting changed.

The users are encountering the same issue even on exporting the data using CN41- Evaluation - Export- MS Office project (MPX) route.

How can I retain the same dates as those in SAP?

Thanks and best regards