Hello Gurus,

we have an issue with our mass upload tool which is Z programme made earlier. The one we use to upload vacation buy / sell elections on IT0377. By using this t-code, the quotas are then automatically adjusted on IT2006. However, for Countries ABC & XYZ quotas on IT2006 are in hours, but the vacation buy / sell adjustment is in days.So the automatic adjustment for Countries ABC & XYZ employees did not work correctly.

Example: For XXXXXXXX employee,

1. Original Vacation Quota = 288 hours (24 days @ 12 hrs/day)

2. Elected to Sell 5 days

3. Upload program automatically adjusted IT2006 by 5hoursinstead of 5 days, so now incorrectly shows 283 hours.

Requesting you to please help me out in this case.

Best Regards,

Rajas

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

0 Answers