on 06-01-2009 4:10 PM
Hi,
I am posting asset acquisition in F-90. We have activated new GL concept.
Now when i post the entry and try to save it, it gives following error:
Balancing field "Profit Center" in line item 001 not filled
Message no. GLT2201
Cost centre field and profit centre are displayed. But it is locked (greyed out).
I know that acquisition of assets is not a cost & cost centre is not applicable and i do not want to create internal oder / WBS in for direct asset acquisition in F-90.
So tell me how to handle this situation.
Solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is it necessary to modify the field agreement for KOSTL?? I have activated this field. I am trying to change it but it is impossible.
Path:
Integration with the General Ledger --> Additional Account Assignment Objects --> Activate Account Assignment Objects
And I do not know if this change is the final solution.....
Please
Check the config
Integration with the General Ledger > Additional Account Assignment Objects > Specify Account Assignment Types for Account Assignment objects
There should be 2 enteries
Account Assignment Object: KOSTL
TTy: *
Account Assignment Type: Depreciation Posting
Account Assignment Object: KOSTL
TTy: *
Account Assignment Type: APC Posting
also check if Cost Center and Profit Center field status for Vendor Recon G/L and Asset is not supressed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I went into additional account assignment objects --> Activate account assignment jects. There are three fields (active, balance sheet, agreement) for giving "ticks"
Third field (agreement) is greyed out. I need to untick the it. so tell me how to open the third field so that i can untick it.
Hello all,
I have exactly the same problem. I have implemented new general ledger and controlling with PCA and the inheritance of profit centre has been established by segment.
When I try to acquire an asset using the transaction F-90, the system deliver the same error.
I can not understand the problem, because with other operations the system works properly, but in this case the system do not bring the cost centre from the asset.
I have tested all things from this forum and nothing fix the problem.
Could you help me with this??
Thanks in advance.