Hi,
I want to plan extra 5% for some of the components ( raw materials) extra than bom quantity. But during production order creation the component quantity should be as per BOM only.
I dont want to consume extra against the same orders. how to handle this with planning and not during consumption.
If i am using component scrap functionality it is also showing extra 5% during production order creation which i dont want it.
please suggest.