Prevent WBS element change with Planned Order and Production Change

Former Member
0 Kudos

When amending a Planned Order (MD12) or Production Order (CO02), is there a way of preventing

changes being made to the WBS element field ? I have looked in the IMG (SPRO) and cannot see

anything.

Any suggestions ?

Regards.

Phil.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

SHD0 worked, thanks.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

There is no setting in SPRO for this but you can do this with transaction variant through SHD0 for MD12 and CO02 here make WBS element field as out put only.

I hope it will also work for you.

Regards,

R.Brahmankar