Rule Bases Check and CTP Settings

Dear Experts,

I want to run Rule based ATP and CTP together in the system. As far as i know the system of each of these are typicAl and i am not able to run both together. Please guide me for any settings to be maintained to run the same.

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jun 01, 2009 at 11:42 AM

    Prashant,

    First, make sure RBA works, and CTP works, independently. I won't go into setup for each of these, which are pretty extensive all on their own.

    I don't know what you are using for rules, so I will give you some general ideas. You will have to decide how you want it to work. For RBA & CTP, it usually makes most sense to run RBA immediately, and when none of the RBA proposals give a solution, then you execute production (CTP). If you were to invoke production first, you will typically find a solution immediately and never get to the RBA step. The trick is to have RBA call production on the last step of the last rule.

    So, in IMG>APO>GATP>General Settings>Maintain Check instructions do product check first (well, unless you are doing allocation, but that is another story). Tick Activate RBA, start immediately. This gets RBA running first. It will do all the product checks you have configured in your RBA. Set the Production part as 'Availability check only, no production'. A bit counter-intuitive sounding, thanks SAP!

    Logically, the final rule you determine (after failure of all previous rules) will be a location determination rule, where the system decides where you are going to manufacture the parts. (you should already have determined product and version). On the final location determination rule, you assign a location determination activity (which you defined in /SAPAPO/RBA04>Profiles and Parameters>Location determination activities). Within the Location determination activity, you invoke production. Within the activity, you define Start Production as 'Availability check first, then production', on the assumption that you haven't checked this location yet for standard product check.

    This is one way to use both RBA and CTP. There are probably others, but I have used this successfully.

    Rgds,

    DB49

    Add comment
    10|10000 characters needed characters exceeded

    • Hello DogBoy 49.

      I made a RBA scenary very similar to your example.

      2 rules:

      1) First using calculation profile limiting in 15 days, Availiability Check only.

      2) Second rule limiting 120 days, production directly.

      The problem i encountered was these controls(Start Production) are inside the location determination activity. Who is only used if you have substitutions.

      I tried to insert directly in /sapapo/rba04 a substitution plant to same plant:

      Plant: 1001 Substitue Loc: 1001 Activity: 10(Check avaialiability only)

      Plant: 1001 Substitue Loc: 1001 Activity: 20(Production Directly)

      But don't work. Can you sugest another way?

      Best Regards

      Marcelo

  • avatar image
    Former Member
    Jun 01, 2009 at 07:08 PM

    Hi Srivastava,

    For settings for rules based ATP settings, please refer to the below link

    http://help.sap.com/saphelp_scm70/helpdata/EN/fb/e6783739e6ff5de10000009b38f8cf/frameset.htm

    Regards

    R. Senthil Mareeswaran.