Hello,

Does anyone one how the computed PDT in WPDTC, is computed ? and i mean the blue one..

its very strange !!!

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

The planned delivery time is calculated from the arithmetic mean of the delivery times that were determined from the difference between the purchase order date and goods receipt date.

The arithmetic mean is created at the following levels:

Info record / purchasing organization / plant / vendor / vendor subrange / material level

By default, a weighting of partial deliveries is included in the mean calculation of value. This weighting can be switched off when the report is started. Other mean values may be produced, however.

Different mean values may be produced for the same folder (for example, purchase info records) by creating the mean values for the planned delivery time on a very specific level.

It is possible to display these critical data records using the relevant radio buttons. It is then up to the user to select the value for the planned delivery time.

Thanks & Regards

Kishore

Answers (2)

Answers (2)

paul_shrewsbury2
Contributor
0 Kudos

For future reference in case you did not know, if you have a question about any field in a report such as this one, select the field and press the F1 key. It will give you the description of the field as shown by Kishore.

Regards

Former Member

Of course i read the F1 help, but some results doesnt make any sense. Look at the link jpg i uploaded. The last blue nine is the mean of the above ? i dont think so...

[http://www.mypicx.com/uploadimg/438184915_05292009_1.jpg]

paul_shrewsbury2
Contributor
0 Kudos

Take a look at this link:

[WPDTC|https://websmp230.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1141142]

This will give you a little more information.

The different colors mean something, but I have not found a legend key yet.

Regards

Former Member
0 Kudos

I cant take a look to this link, it ask me for a password.

The f1 help says this:

"The arithmetic mean is created at the following levels:

Info record / purchasing organization / plant / vendor / vendor subrange / material level

By default, a weighting of partial deliveries is included in the mean calculation of value. This weighting can be switched off when the report is started. Other mean values may be produced, however"

My first question is how do you switch this off ? i dont see any option...

and the second one, is any ABAP expert here that can understand the function module "PDTC_EVALUATION" ?

I think that there's the answer...

Regrards.

paul_shrewsbury2
Contributor
0 Kudos

The link is for a note on the SAP Marketplace site. You must have an ID to access Marketplace. Consult your Basis group to get an ID. If you are not a customer but are a consultant, this may be hard.

Try this thread for an earlier post:

[Lead Time recalculation/update|]

Regards

paul_shrewsbury2
Contributor
0 Kudos

After running the WPDTC report, click the "Expand" button in the toolbar. It then shows you columns where all the source data came from with weighting factors. Doubt this is much help, but I am still looking because I would like to use this new transaction as well.

Regards