Hello expert,

We are implementing ISU-Electricity project & currently facing problem regarding movement types.

After full removal of meter we want following flow

RemovalGridPlantStorage location (Stock)

Which movement type we should use in every step.

Also for installation (reversal) of meter what would be the movement types.

The problem we are facing is that issuing a meter out to a Service Order is fine but receipting it back into stock is proving difficult

-


Nitin