Dear Gurus,
is there a way to stop PO creation with reference to contract when contract target quantity exceed?
Warm regards,
Fuffo
Please try to restrict with Quality Info record
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ciao Fuffo,
spro -> material management -> purchasing -> defien attribute of sysetm message, select :
version 00
appl. 06
number 078 (Target quantity exceeded by & &)
set the catergory of the message to E... and save
now when ypu create a PO in reference to MK contract and the quantity is greater than the contract quantity System stop you with an error message.
Buona Giornata
Mauro
hi Mauro,
Thank you for your rely, it helped me.
But you have missed a node, the right road should be:
spro -> MM -> purchasing -> enviroment data -> define attributes of system message
just as a reference for the people who can not find the right place
Wendy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.