How to make Purchase order number field mandatory in VA01

Former Member
0 Kudos

hI ,

Can anyone tell me the process of making PURCHASE ORDER NUMBER field mandatory in VA01 tcode.

Is it possible through customizaton ( spro ) , please let me know.

Thans & regards,

Hari priya

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member

Hi

chek in LOg of incomplete terms in OVA2

SPRO>>>>sales and distribution>>>>>basic functions>>>>log of incomplete terms

here define incomplete procedure for sales header and then select the procedure as 11 standard order and now select the fields and then insert

VBKD BSTKD PO number KBES 01

regards

Former Member
0 Kudos

Hi,

Go to OVA2 t-code and select sales header, then select 11 standard order, then select fields and there is PO, make it as warning, so it will become mandatory now.

Thanks,

Raja

Former Member
0 Kudos

See i want to Make PO Number and PO Date Mandatory in VA01 Transaction, the system has to throw error message "Please Enter PO Number". how to do this via Customization in SPRO.

Please mention the steps clearly.

Regards,

Hari Priya

Former Member
0 Kudos

Hi

SEE THEN MAKE A SCREEN VARIANT IN SHD0 FOR VA01

regards

Former Member
0 Kudos

hi rithivika ,

kindly tell me the steps to create screen variants for va01.

reagrds,

hari priya

Former Member
0 Kudos

Hi,

For SHD0 you can check

http://help.sap.com/saphelp_nw2004s/helpdata/en/43/132f9803d76f40e10000000a422035/content.htm

http://searchsap.techtarget.com/tip/0,289483,sid21_gci1213076,00.html

But why u want to do this with screen variant? You can add PO number in incompletion procedure. as i suggested earlier.

Thanks,

Raja

Former Member
0 Kudos

hi raja,

i checked in OVA2 tcode ,

table : VBKD

field : BSTKD

des : po number

screen : KBES

status : 01.

waring : tick

seq : 0.

but while creating sales order , error message is not coming in incompletion log.

edit ->incompletin log.

it is showing document is compete even though po number not entered.

regards,

Hari priya

former_member315051
Active Contributor
0 Kudos
but while creating sales order , error message is not coming in incompletion log.
edit ->incompletin log.

it is showing document is compete even though po number not entered.

Check the VOV8 - select your document type, in your case it might be unticked, Now tick the Incomplet message indicator, then try to create sales document in which information is missing, the system advises you that the document is incomplete. this case system wont allow you to save the document if document is incomplete.

Former Member
0 Kudos

Hari,

Your setting for incompletion log is correct.

Did u also checked the tick mark in VOV8 for sales order type?

Retry it once, it should work.

Thanks,

Raja

Former Member
0 Kudos

hi raja,

i checked in vov8 tcode also for my order type.

incomplete messages is ticked.

is there any thing to check in vov8?

Regards,

Hari priya

Former Member
0 Kudos

Hi Hari Priya,

Check in T'code VUA2 and activate the IC dailog box againest your order type and the incompletion procedure for sales header.

Try and revert back.

Regards,

SK

Former Member
0 Kudos

Hari,

Your settings are correct, Agreed with suggestion from Mr Mastan, Change the message type.

Thanks,

Raja

former_member315051
Active Contributor
0 Kudos
incomplete messages is ticked.

also check the same incomplete procedure is assigned to your document type.

As you are successfully assigned that field in incompleteion procedure , and you have ticked incomplete message indicator in document type., then the same procedure need to assign to document type.

Create new sales order, dont maintain PO number and try to save the order, while saving the order system will give u a popup for incomplete messages.

Former Member
0 Kudos

Hi ramesh,

in VUA2 tcode ,

For my order type Incompletion procedure for sales document is different , that why error message is not coming.

now i changed procedur which i maintained in earlier ( ova2).

Now error message is coming..

thank u very much to all of them fr valuble suggestions.

Thanks & regards,

Hari priya