Hi All,

the requirement is that whenever the PO total value is more that 10 k dollar then the system should pop up a message to the po creator. Please let me know which structure can i use which holds PO total value.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    Nov 17, 2016 at 09:26 PM

    classification for release strategy makes use of values from structure CEKKO, so you should give that one a try. For programming questions it is certainly better to tag the question with ABAP Development

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 14, 2016 at 09:40 AM

    The Net amount field is "GNETW" avialable in EKKO.

    Add comment
    10|10000 characters needed characters exceeded

    • Agreed but i need the PO total vale even before the PO is saved because i need to show a message if the PO value is greater than 10 k USD. From where can i retrieve this information before the PO is saved.

  • Nov 21, 2016 at 08:28 AM

    Thanks Jurgen,

    I have found GNETW field in CEKKO. Till now I have asked my ABAPer to use the logic of summing all the PO line item values to get the PO total value during PO creation. Will check with the ABAPer if this logic can be replaced and this filed can be instead.

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 02, 2017 at 06:02 AM

    Answere is provided by Jurgen in this thread.