Component assignment

rajesh_sutar2
Active Contributor
0 Kudos

Hi Experts,

Can anybody please tell me,

I have 4 component in BOM say A,B,C & D.

In Routing there are 5 operations.

My requirement is as follow

1. For 0010 operation I need component A,B & C

2. For 0020 operation I need component A & D

3. For 0030 operation I need component B & C

4. For 0040 operation I need component A,B & D

5. For 0050 operation I need component A,C & D

Please tell me how I can assign these component to that operation.

Raja

Accepted Solutions (1)

Accepted Solutions (1)

Ritz
Active Contributor
0 Kudos

Raja

Hi Raja,

As mentioned above if al this 4 components A,B,C,D are maintained as a single line items in BOM you can assign them only to one operation in routings.

But if the requirements is like that you need different quantitys of A,B,C,D at different operations you can maintaion them as as a seprate line items in BOMu2019s and allocate them to respective operation.

Ex of BOM can be

allocated to routing operation

BOM position component quantity

0010 A 1 0010

0020 B 1 0010

0030 C 1 0010

0040 A 1 0020

0050 D 1 0020

0060 B 1 0030

0070 C 1 0030

0080 A 1 0040

0090 B 1 0040

0100 D 1 0040

0110 A 1 050

0120 C 1 0050

0130 D 1 0050

Hope you got your answer.

Regards

Ritesh

Edited by: R S D on May 27, 2009 11:28 AM

rajesh_sutar2
Active Contributor
0 Kudos

Hi SmanS & RSD,

Smart answer.

If I maintain BOM with multiple line item,then this BOM quantity will get copy to production order.

Suppose Base quantity of FG BOM is 1unit & I mantain component quantity 1 unit for all multiple component, then when I create production order for say quantity 10,then in BOM all component get multiple quantity i.e 10.

Means I maintain A component 4 times in BOM,then it shows total 40 unit in order. As my requiremet is only 10 unit of A for producing 10 unit FG material.

Then what to do. I have to always change quantity in order.

Raja.

Former Member
0 Kudos

Raja,

In this case you need to maintain the quantity of the component in the fraction so the total quantity won't exceed 1 ea.

i.e.

0010 A 0.5

0020 A 0.2

0030 A 0.15

0040 A 0.15

Or make the base quantity of the BOM as 10 or 100 & maintain the component in multiple line items with separarte quantity so that it won't exceed the required quantity 10 or 100 all together.

I.e. For base quantity of 10,

0010 A 5

0020 A 2

0030 A 1.5

0040 A 1.5

Hope this helps you.

SmanS

Edited by: SAP PP Consultant on May 27, 2009 11:44 AM

rajesh_sutar2
Active Contributor
0 Kudos

Hi SmanS,

Thanks a lot.

Ritz
Active Contributor
0 Kudos

Hi raja,

Although your question is already answered,

The solution i proposed was valid in case when you need altogether new quantity of component on different operation.

But if your component is appearing only one time with one quantity , physically how you can assign component to one operation and after completion of operation how you expect it to be same as it has been before start of operation (i.e its attribute doesnu2019t got change as you must have perform some machining/assembly with it)

Just consider the case you explained, if you are assigning A,B,and C to 0010 so the out put of operation 0010 will be certainly different then same A,B,and C.

If you want to recognize this out as a different material number it will result in addition of BOM level as well as routing level.

Regards

Ritesh

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

Split the item required quantity into how many time u reqired and enter in the bom

say bold you need 40 nos. for first operation 200 and second operation 200.

you create two line item for the same material with the split in the required base qty

Edited by: raj on May 27, 2009 11:22 AM

Former Member
0 Kudos

I think in your case you should maintain the component multiple times as items of your header BOM. This way you will be able to assign it multiple times in the routing.

Try & revert back

Former Member
0 Kudos

Raja,

Multiple assignments of single line item of the BOM is not possible in R/3.

To map your requirement you need to maintain the item in multiple lines & assign to the desired operations.

Hope this helps you.

SmanS

rajesh_sutar2
Active Contributor
0 Kudos

Hi,

Thanks for your quick reply.

Can you please explain how to maintain the item in multiple lines & assign to the desired operations.

Raja.

Former Member
0 Kudos

Raja,

In your example the component A is the part of FG BOM with quantity as 20 KG overall.

While entering it in the BOM you need to maintain the A 4 times with separate quantity.

I.e.

0010 A 7 kg

0020 A 3 kg

0030 A 4 kg

0040 A 6 kg

Now assgn these line items to individual 4 operations in the rotuing.

Repeat the same for other components too.

Hope this helps you.

SmanS