Hello guys,

since a few days we have a big problem with our system. After a undefined time all workprocesses are full by executing the report SAPLSPOX.

--> they try to create an output to table TSP01

SURE the solution is to run a job which deletes old printouts (RSPO0041)

But I'm having this problem since days.

NOW I want to increase the number of max. spool requests????

Or is there a better solution????

It's very busioness critical at the moment.

Cheers

christian

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

we have solved this issue by upgrading Oracle from 10.2.0.2 to 10.2.0.4. SAP has investigate it on our system and it had to do with oracle bug 6376915. In this case, please refer to SAP note 1166242 and try to fix this bug or upgrade to 10.2.0.4.

Former Member
0 Kudos

Christian,

Check Note 108799 - How many spool work processes for each instance?

Thanks,

Sushil

Former Member
0 Kudos

hi

First goto T-code SPAD >> Adminitstration >> Clean up spool >> and delete the older spool request .

The schedule the standard job SAP_REORG_SPOOL (RSPO0041) and job

SAP_SPOOL_CONSISTENCY_CHECK form sm36 . See note 16083 for more details.

Cheers

Anish

christian_laber2
Participant
0 Kudos

Hello together,

thanks all four your help.

I have changed the max. spool requests from 32000 to 80000 and I run into this problem last evening again.

Are there any other settings to change. Buffers or something like that........

Please help me because of system standstill each time we run into this situation.

Cheers

Christian

Former Member
0 Kudos

Hi Christian,

as mentioned above, have a look at this two notes:

Note 48284 - System can no longer create spool requests

Note 48400 - Reorganization of TemSe and Spool

there should be all the information you need to solve the problem

Regards

Bjoern

Former Member
0 Kudos

If you have followed the Notes 48284, 108799 then there should not be much problem. you can consider TemSe re-organziation too Note 48400 - Reorganization of TemSe and Spool to double check if any inconsistency is there.

However, what kind of print server you have, i mean, Are all the printers in the network ? sometimes problem comes while querying the printers from the print server and spool work processess hang in querying the spool server. in SPAD you have an option to check/uncheck the 'query to host spooler' for any specific printer

Former Member
0 Kudos

In addition to what already has been pointed out:

Did you check your spool system at operating system level? Any bottlenecks there?

Former Member
0 Kudos

Hello Cristian,

did you solve the problem that program SAPLSPOX occupies all DIA workprocesses. We are running in the same problem.

Kind regards,

Rene van den Brand

Former Member
0 Kudos

Note 48284 - System can no longer create spool requests

and regarding workprocess getting full, how many spool work processes defined in your system ? If it is only one, then you might want to have two or three