Former Member
May 26, 2009 at 04:44 PM

Want Automatic scheduling in case I partially confirm the activity

118 Views

Hi Experts,

I have one network with two activities having FS relationship with duration for ex.10 & 20Days.

Activity 1: ES = 01-01-2009 & EF = 10-01-2009 (Date -Month - Year format)

Activity 2: ES = 11-01-2009 & EF = 30-01-2009

I havedone the following settings:

1) Adjust Basic Dates

2) Automatic Scheduling

3) In confirmation parameters - Propose dates

Now I had done the partial confirmation of activity 1 with actual start 03-01-2009 & Actual Finish 11-01-2009 & forcast duration 2 days

Now when i save the NW or Project but system dose not do the automatic scheduling Earliest dates remain same .For this I have to do manually

Can some one help so that the system schedule automatically & the result would be as

Activity 1: ES = 03-01-2009 & EF = 13-01-2009

Activity 2: ES = 14-01-2009 & EF = 03-02-2009

Regards,

Deependra