Hi Experts,
I have one network with two activities having FS relationship with duration for ex.10 & 20Days.
Activity 1: ES = 01-01-2009 & EF = 10-01-2009 (Date -Month - Year format)
Activity 2: ES = 11-01-2009 & EF = 30-01-2009
I havedone the following settings:
1) Adjust Basic Dates
2) Automatic Scheduling
3) In confirmation parameters - Propose dates
Now I had done the partial confirmation of activity 1 with actual start 03-01-2009 & Actual Finish 11-01-2009 & forcast duration 2 days
Now when i save the NW or Project but system dose not do the automatic scheduling Earliest dates remain same .For this I have to do manually
Can some one help so that the system schedule automatically & the result would be as
Activity 1: ES = 03-01-2009 & EF = 13-01-2009
Activity 2: ES = 14-01-2009 & EF = 03-02-2009
Regards,
Deependra