Hello Gurus,
When I create a PO with item category D (service), the delivery completion Indicator is not seen. But for the same document type when I create a PO without item category D I can see the delivery completion indicator. My Challenge is to get this delivery completion indicator for Item Category D. Can some one help me.
Regards
SS
Thank you Very Much. This can be done. We need to activate Delivery Completion Indicator for the Screen layout of PO PT9F. Be careful there are Two Delivery Completion Indicators in PT9F. Tick Both of them if you want to see Delivery Completion Indicator for item category D (Services).
Regards
SS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In standard SAP, there is no delivery completion indicaotor for service PO.
Regards,
Prabu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.