can anybody explain about scope of planning ?

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

thnks all

Former Member
0 Kudos

Hi pls check the reply in one of the threads that Mr. Dharma gave:

Scope of planning is used to run mrp for

1. Several plants

2. One mrp area

3. Multiple mrp areas

4. Combination of plant & mrp area

To create a scope of planning use tcode OM0E.

1. Give alphanumeric no. to create scope of planning.

2. Assign your Plants & save.

3. Use tcode MD01 to run scope of planning, enter your scope.

4. Make tick mark in parallel processing in initial screen of MD01. (bottom)

5. Now you can see the result in MD04.

6. Before run MRP, input your server name in Define parallel processing in MRP in customized setting.

Former Member
0 Kudos

I u want to run MRP for materials of mpre than 1 plant, you can go for scope of planning..

THe customizing path is SPROProduction>Material Requirements Planning-->Define Parallel Processing in MRP

In OM0E you need o enter all the plants..and based on this scope of planning you can create variants which can be scheduled using MDBT to run in back ground.

former_member335796
Active Contributor
0 Kudos

Hi,

Refer the below thread:

Best Regards,

Siva

Former Member
0 Kudos

Hi

First you need to create the Planning scope in OM0E transaction code , then include what are the plants you want to run the MRP in the Planning scope. Use MD01 and enter the scope of planning and run the MRP.

Thanks

S.Murali

Former Member
0 Kudos

The scope of planning ia mainly used to group the number of plants or MRP area.

If you want to run the MRP for multiple plant, you can create Scope of planning for all those plants and in MD01 you can enter that scope of planning to run the MRP.

Regards,