IndReq ZCC and VSF

Former Member
0 Kudos

Hi all,

I have seen ZCC of IndReq in MD04, usually it display as VSF after forecast is being loaded through APO.

I have tried to change the material master strategy group from ZC to 40, and it will change from ZCC to VSF after MRP run.

Pls can you tell me what is ZCC and what are the difference between ZCC and VSF?

Thank you

Accepted Solutions (0)

Answers (1)

Answers (1)

jpfriends079
Active Contributor
0 Kudos

ZCC (OVZH) is non-standard requirement type.

As non-standard req type is organisation specific config and it is not common across applications.

Please check what requirement class (OVZG) is getting determined for req type ZCC.
Whether that is a standard one or non-standard?

Say, let take an example for reqt type VSE, the req class is 103.

Thanks,
JP