Leave not posting to IT2001

Former Member
0 Kudos

Dear All,

Scenario : Employee's Approved leaves are not posting to IT2001. This is happening for only some cases.

History : As told by SAP consultant (OSS) , I removed the Binding in Administrator Check.

What can be the reason ?

i) If Payroll control record is in Payroll Correction , Will system allow to post the leave.

It is getting updated after more than 3 - 4 Days.

Regards,

Kamal Rawal

Edited by: Kamal Rawal on May 25, 2009 12:42 PM

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

I am closing this thread as it is open for too long.

Former Member
0 Kudos

Hi,

I faced the similar issue.

I was approving the leave in the portal and it was not reflecting in IT 2001.

The reason was ,I had opened the HR master data-maintainence view at that time(via PA30) when I was processing the leave in portal.

I closed the maintainence view of HR Master and it worked!!.

Please try in the similar fashion.

Thanks

Manish

Former Member
0 Kudos

please consider the below points

1) is it updating in the system late or the status "approved is happening late"

approve for a person , the leave, and then manually run the program to post.

If posting happens , then the problem should be with the background schedule program or employee records are locked.

If posting doesnt happen, then check once approved why the status is not changed or how long its taking for the status to get changed

Former Member
0 Kudos

It is updating late. Taking more than 2 -3 days.

Regards,

Kamal Rawal

former_member75029
Contributor
0 Kudos

System will allow in the payroll correction mode offcourse. Please check with workflow why it is updating after 3,4 days.

Afrasyab