on 05-25-2009 7:10 AM
Hi!
What are the Transactions i need to Run while packing Finished Goods in Make To Order Scenario.
(ie. COWBPACK,COWBHUWA etc)
since i belong to SD can you just reply back transactions serially so that i'll fiollow the same sequence.
i need to pack material in HU02 for a particular order(MTO)
Regards.
Amol
Dear,
1.You have to Created Packing Instruction for a material in POP1 transaction
2.The in the Material master Basic data you have to assign the Packing Material group for both the header material and the packing material. Both to be in same packing material group.
3.The use tcode COWBPACK for creating the packing with Handling units
4.Then use tocode COWBHUWE to make the receipt.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Brahmankar,
i have created SO->
i have run MRP.->
I have confirmed production order.->
Then i have packed with COWBPACK-> then HU no "1000001730" is generated->
then i did COWBHUWE & posted it.
But, When i am assigning that HU to my DELivery document, its giving me error as
"HU 1000001730 is assigned to an object that cannot be processed here."
any step i missed???
kindly guide
Regards,
Amol
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.