Dear Experts,

While creating workcenter throgh CR01 or IR01 the workcentre categories PM01,PM02 and PM03 is not appearing in selecting criteria.Can you please tell how to customise it in SPRO.

AR

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Amit ,

Work center Categeory are maintain like

Machine

Stat. WkCtr MchneGrp

Labor

Stat. WkCtr LaborGrp

Plant maintenance

Project management

Production line

Pls select the following path in SPRO

Plant Maintenance and Customer Service-->Maintenance Plans, Work Centers, Task Lists and PRTs->

General Data---->Define Work Center Types and Link to Task List Application

here you can select the categeory and go to application tab and select option (I) Maintenance task lists

or as per your requirement you can select the Application.

Rahul.

Answers (3)

Answers (3)

former_member681489
Active Participant
0 Kudos

Hi dear

work center catogries are the work centers by their category (for example, production work center, maintenance work center).

The work center category determines which data can be maintained in the master record for the work center.

while pm01 ,pm02 are the control keys for the operations in any maintenance order

work center catogries distinguish between . labour, machine , maintenance, etc.

and for defining these u can follow

Plant Maintenance and Customer Service --> Maintenance Plans, Work Centers, Task Lists and PRTs --> Work Centers --> General Data -->

jitender

Former Member
0 Kudos

Dear All,

Thanks for your valuable reply.

Can you please explain,

How to create main work centre & work center.

How can we differentiate the two after creation.

What is the use of work center hierarchy.

AR

Edited by: Amit Rana on May 25, 2009 11:30 AM

Former Member
0 Kudos

Hi,

PM01,PM02 & PM03 these values are Control Keys not Work Center Categories.

If you want to define the Work Center Categories follow the IMG Path mentioned below,

Plant Maintenance and Customer Service --> Maintenance Plans, Work Centers, Task Lists and PRTs --> Work Centers --> General Data --> Define Work Center Types and Link to Task List Application

regards,

Venkatesan Anandan

Edited by: Venkatesan Anandan on May 25, 2009 7:20 AM

Former Member
0 Kudos

For plant maintenance ... work center category should always be 0005-Plant Maintenance ... unless u specifies a new one in customizing.