Can anybody explain what is Netting of Planned Indipendent Requirement?

Regards,

Basavaraj

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on May 26, 2009 at 07:07 AM

    Dear All,

    Thank you very much for the detailed explination.

    Now i have 1 question.

    I am using Strategy 50.

    I had PIR of 100qty for April month,in that 90qty have been consumed by sale orders.Now I left with 10qty PIR for april month.

    If i create sale order for May month system consuming PIR of May month.April month PIR remain unchanged.

    Now my question is, can i delete April month PIR?Bcos now system is not consuming this PIR,there is no use this PIR now.

    Thanks & regards,

    Basavaraj.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 25, 2009 at 06:50 AM

    HI,

    In the Define Planning Strategy configuration you have something called Planning Indicator which will decide whether the PIR's to Netted OR not.

    Goto Tcode : OPPS and select one of the strategy and goto details you will fine the above indicator under Reqts Type of Ind Reqts.

    Example :

    Planning Indicator

    The planning indicator determines which of the following is valid for the planned independent requirement:

    Net requirements planning

    Gross requirements planning

    Individual requirements planning

    Hope this will help you.

    regards

    radhak mk

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 24, 2009 at 10:48 AM

    Hi,

    I've never seen this expression in SAP online help / OSS notes. Where did you here it?

    There's net requirement calculation in SAP: it means you consider your stock during planning (MRP run), whilst gross requirement claculation means you do not consider your stock level during MRP run - this can be used in MTS environment.

    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d27b744af11d182b40000e829fbfe/frameset.htm

    In planning strategy 40 SAP considers both PIRs and SOs. SOs consume PIRs based on material master settings (backward/forward consumption). Maybe the expression you are asking is in connection with this (SOs quantities reduce PIR quantities and that's why SAP calculates with the SO quantities and with reduced ("netted") PIR quantities).

    http://help.sap.com/erp2005_ehp_04/helpdata/EN/cb/7f93e643b711d189410000e829fbbd/frameset.htm

    In this thread you can see that this terminology is used for PIR quantities reduced by SO quantities:

    netting-pirs

    So, it seems SO quantities reduces PIR quantities and this is called as "netting" (by certain people).

    Regards,

    Csaba

    Edited by: Csaba Szommer on May 24, 2009 12:51 PM

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.