Result recording in Preventive maintenance and calibration

Hiiiii Experts,

I need your help.I have created a plan, scheduled it and then order is also generated.Now once the order is generated wheather Preventive or calibration, How I enter ther result into sap.There are some results which are only texts and few are quantity.

Please tell me the steps to record the result.

Regards

Brijesh

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on May 23, 2009 at 07:47 AM
    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on May 25, 2009 at 03:20 AM

    Hi

    Wht are the MIC u r used in Task list referance to that MIC you have to recored it , mostely we are using visual inspection for Calibration

    If you are still dought plz revert to me

    Regards,

    Utkarsh

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi

      Sorry for the wrong post... i thought ur looking for caliberation process and its inspection

      According u to ur query, as an Example...

      Basic Scenario - Need to create a Plan, for taking pump vibration measurement in every three months...

      Step 1 : Create a Equipment or General Task List (In Operation - Vibration Inpection at different load like 60/80/100) so u have 3 operations to be done once in three months) in IA01

      Step 2 : Create a Measuring point for the equipment Pump, where ur taking vibration measurement in IK01, Here u can give upper limit and lower limit.. such that when the user try to enter the measurement more than the value.. it will give a error message...

      Step 3 : Create a Maintenance plan.... IP01/IP41

      1. Cycle - 3 months

      2. Enter the Equipment and the task list

      3. Scheduling Period - 1 yr

      4. Save it

      Step 4 : Schedule the plan in IP10 (You will be getting for call objects for one year)

      Step 5 : Once the date as been reached - Order will be called... Go to IP10, enter the Maintenance plan no and select the call and click display

      Step 6 : take the respective measurements

      Step 7 : Enter the measurements in the measuring documents (IK11)... Save it

      Step 8 : In the Order, enter if u have used any material and do Goods issue

      Step 9 : Do Confirmation in IW41

      Step 10 : Complete the Order, using TECO and Business Complete...

      Hope so u r clear...More details check the Help.sap.com...

      - Pithan

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.