There are two plants.

We receive Combined Sales Order for both the plants.

What is the best MRP run so that it matches following constraints:

- it should consider reorder level/safety stock

- It should consider available stocks

- It should also consider Sales Order Qty (external demands)

- the MRP result must have the reference of Sales Order

- Finally, is it possible to club all PR in one ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

There is a supply plant field in every position in teh sales order, so it should point to the right plant.

So 1-3 Yes,

4, if you use a MTO strategy, then the planned order will point to the sales order,

5 , I am afraid NOT , at least as you have described the process

What is the best MRP run so that it matches following constraints:

1- it should consider reorder level/safety stock

2- It should consider available stocks

3- It should also consider Sales Order Qty (external demands)

4- the MRP result must have the reference of Sales Order

5- Finally, is it possible to club all PR in one ?