There are two plants.
We receive Combined Sales Order for both the plants.
What is the best MRP run so that it matches following constraints:
- it should consider reorder level/safety stock
- It should consider available stocks
- It should also consider Sales Order Qty (external demands)
- the MRP result must have the reference of Sales Order
- Finally, is it possible to club all PR in one ?
There is a supply plant field in every position in teh sales order, so it should point to the right plant.
So 1-3 Yes,
4, if you use a MTO strategy, then the planned order will point to the sales order,
5 , I am afraid NOT , at least as you have described the process
What is the best MRP run so that it matches following constraints:
1- it should consider reorder level/safety stock
2- It should consider available stocks
3- It should also consider Sales Order Qty (external demands)
4- the MRP result must have the reference of Sales Order
5- Finally, is it possible to club all PR in one ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.