abc indicator

Former Member
0 Kudos

Hi All,

how to update ABC incidator in the material master automatically, After system change the ABC incidator for all the material, execute in the T.Code MC40

do any configuration we need to do,

Thanks

vraj

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member196398
Active Contributor
0 Kudos

Raj,

If you are looking at updating the ABC indicator in MRP views then you need to schedule the Program "RMCBAB20" in background if you want for a list of materials to be done. If it is few materials in transaction MC40 you can use the "Change ABC Indicator" function button in the report output to change for specific materials.

Regards,

Prasobh

former_member196398
Active Contributor
0 Kudos

Raj,

Can you confirm if you want to updated the ABC indicator for Physical Inventory cycle in material master?

If so, here is exerts from Help,

Title

ABC Analysis of Cycle Counting (Physical Inventory)

Purpose

Report " RMCBIN00" runs an analysis for the chosen material types in the cycle counting method of physical inventory.

Prerequisites

Before running the analysis, you must define the valid cycle counting indicators in the Customizing system of Inventory Management and define the percentage allocation of the materials to the individual cycle counting categories.(Transaction OMCO)

You can also directly change the percentage values via the indicator Change CC percentages on the initial screen of the analysis.

To set the cycle counting indicator for a material, you need authorization to change material master records (authorization object Material Master: Plant, activity 02).

Please go through the Program "RMCBIN00", using transaction SE38 for more details,

Regards,

Prasobh

Edited by: Prasobh Karunakaran on May 22, 2009 12:49 PM