Dear Gurus,

I have one finishe mat F1 with strategy 50 & 2 Semi finished mat S1 with Strategy 11 & S2 Strategy Blank.

S1 will be produced from S2.

If i give PIR for 100 qty for F1, system creating Plnd order of 100qty for S1.

I have S2 stock of 10qty.

My requirement is if i have stock of S2 system should not consider the stock,it should create plnd order of 100qty for S2.

But in my case system considering the stock & it is creating plnd order of 90qty for S2.

Kindly suggest me what setting i need to do so that system creats plnd order of 100 for S2.

Thanks in advance.

regards,

Basavaraj.