Dear Gurus,
I have one finishe mat F1 with strategy 50 & 2 Semi finished mat S1 with Strategy 11 & S2 Strategy Blank.
S1 will be produced from S2.
If i give PIR for 100 qty for F1, system creating Plnd order of 100qty for S1.
I have S2 stock of 10qty.
My requirement is if i have stock of S2 system should not consider the stock,it should create plnd order of 100qty for S2.
But in my case system considering the stock & it is creating plnd order of 90qty for S2.
Kindly suggest me what setting i need to do so that system creats plnd order of 100 for S2.
Thanks in advance.
regards,
Basavaraj.