Skip to Content
avatar image
Former Member

Problem with Workflow standar parked documents WS10000051

Hi,

I have configured a standard parked document workflow(Version 7.50 Hana). When I release the document my work item has a status error:

When I release the document it should post, but it doesn't.

I execute manually method FIPP.POST using Trx SWO1, and it did the posting successful.

I did some research and I found a sap note 2345795, but after implementation I continue getting the same error.

can someone help me?

thanks in advance.

errorwf.jpg (209.9 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Nov 14, 2016 at 07:35 PM

    Hi,

    Thank you for your reply, It is the standard Workflow, I made the configuration WS04000004 to complete document FI, for release I used WS10000052, I mean:

    variant.jpg

    levels.jpg

    however, I solved the problem by unchecking the option Advance with dialog in the task definition of the Worflow Builder under the tab Details.

    thank you guys!

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 14, 2016 at 08:23 AM

    Hi,

    Could you please share the details of the particular step which is going in error.

    A screenshot will help.

    Regards,

    Sankar

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 14, 2016 at 10:07 AM

    Hi,

    you should check the binding of the workflow step <--> task

    I think a parameter is missing its &

    Kind regards, Rob Dielemans