Budgeting using ECP data

hi

is it possible to copy budget values from ECP data?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    May 20, 2009 at 10:03 AM

    Hi Surya

    I just wanted to ask that can i use this rough cut plan data as my budget values...

    i mean is there any way that at the time of budgeting i can get those values , is it possible to use those plan values as my budget values before sales order creation , like from cj40 i can plan values(Structural planning) and i can use those values in cj30.

    Thanks

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      yes you can............

      this planned values can be copied directly as your budget with the t-code IMCCP3

      you have to transfer .....the planned values to buget values ....there you can give the % of the values

      example :100% planned as budget or 90% values of planned as budget ...........u have an option also of converting the planned to budgeted.

      Regards

      surya

  • avatar image
    Former Member
    May 20, 2009 at 09:56 AM

    question is not clear...

    as far as i understood, ecp is as a rought cut plan for creating a quotation for the system..

    this rought cut cost plan can be use as cost plan, once the quotation is converted to order.

    based on this cost plan , budget can be allocated, the same cost plan can be converted to budget also

    hope so, i am not the track of ur question

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 20, 2009 at 10:00 AM

    Go to CJ30, Click on "Edit --> Copy View " from the pop-up select "05" (Planned total).

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 20, 2009 at 11:34 AM

    i kept it as 100% b ut values are different

    in ECP it is 1200 EUR and in CJ30 planned values is coming 2000

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,,

      Use tcode IMCCP3 to copy planned cost to budget.In your case if it is coming 2000 instead of 1200 i think you are using a costing sheet so system is adding cost on 1200 so it is coming 2000 Please check the costing sheet in your project.

      Muzamil

  • avatar image
    Former Member
    May 22, 2009 at 04:54 AM

    closed

    Add comment