How to post Actual costs

Dear all,

I have number of activities in that i have costs(activities) planned cost is 1lac. But actual am not able get in project planning board. Plz suggest me how to go further, If i miss actual confirmation somewhere.

Regards,

S.Suresh.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    May 20, 2009 at 08:20 AM

    Use CN25 or CN27 to do the confirmation...

    Sarang

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 20, 2009 at 08:43 AM

    Hi,

    Cost activity allows you to only plan cost not to post actuals form projects exg:Insurance expense. so you can't get actual cost through even by confirmation.

    You have post actuals using FB50 or FB60.

    Reg,

    sam

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 20, 2009 at 08:48 AM

    Dear sam,

    Thank you for ur quick response.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 20, 2009 at 06:50 PM

    Hi Suresh,

    1.If you are using Internal Activity to plan Labor Hours then while confirming the Activity system will post actual cost(Controlling document) .The cost is Secondary cost.

    2.For external services it will be after acceptance of service in ML81N.

    3.For external services it will be after MIGO.

    4.For General Cost activities you can get costs after confirmation.For that you can post by FB50 or you can post a controlling document also by various CO tcodes(Manual cost allocation) i think tcode is KB15N .

    Muzamil

    Add comment