May 20, 2009 at 06:57 AM

Milestone function

22 Views

Hi friends,

Using milestone functions, I can change the release status of one activity based upon the status of another activity by using the "Release following activities" indicator.

But this will not stop me from manually releasing the activity. Can I make it mandatory that unless and until I dont change the status of the predecessor activity, I should not be able to release the successot activity?

regards

Pratap.V