Milestone function

Former Member
0 Kudos

Hi friends,

Using milestone functions, I can change the release status of one activity based upon the status of another activity by using the "Release following activities" indicator.

But this will not stop me from manually releasing the activity. Can I make it mandatory that unless and until I dont change the status of the predecessor activity, I should not be able to release the successot activity?

regards

Pratap.V

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

that is not possible in std sap - in std sap manual oiveride is essential to cover contingencies in any business process

you can develop on save exit etc . .