sap pm skip operation

Hi ,

need to skip few operations when order is generated.

Task list contains.

operation 1 , operation 2, operation 3 , operation 4.

ex 15 days preventive maintenance order to be generated .

01.11.2016 first schedule order should contain operation 1 , operation 2, operation 3

16.11.2016 - after 15 days. second schedule order should contain operation 3 , operation 4 on next date .

Is there any way to skip operations as desired using same task list for many equipment's .

Thanks

Ashu :)

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Nov 13, 2016 at 04:37 AM

    Hi Ashu,

    I dont think you can achieve using Single Cycle Maintenance plans, you need to use Maintenance Strategy and assign packages to Operations.

    In your case, Operation 1, Operation 2, Operation 3, should be under one package, then Operation 3 and Operation 4 should be under one package

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 15, 2016 at 07:18 AM
    Add comment
    10|10000 characters needed characters exceeded

  • Nov 15, 2016 at 08:08 AM

    Hi,

    But how operation are selected while generating order , it work on cycle provided (either performance or time based in cycle sets)

    could you please share some example or any link further.

    Thanks

    Ashu :)

    Add comment
    10|10000 characters needed characters exceeded

    • Ashu,

      Create a strategy with two packages:

      • Package 1 - 15 days (hierarchy level 1)
      • Package 2 - 30 days (hierarchy level 2)

      Create your task list and assign OP1/2/3 to package 1, and OP4 to package 2.

      Create a plan and schedule.

      PeteA

  • avatar image
    Former Member
    Nov 15, 2016 at 04:12 PM

    Hi Ashu Aggarwal

    When you create the task list, in operation section, asign one package for all:

    1.-select the button "MntPack"

    2.-Asign the strategy to the operations

    3.- Create a plan

    4.- schedule the plan.

    Remember create your strategy IP11