Hi ,

need to skip few operations when order is generated.

Task list contains.

operation 1 , operation 2, operation 3 , operation 4.

ex 15 days preventive maintenance order to be generated .

01.11.2016 first schedule order should contain operation 1 , operation 2, operation 3

16.11.2016 - after 15 days. second schedule order should contain operation 3 , operation 4 on next date .

Is there any way to skip operations as desired using same task list for many equipment's .

Thanks

Ashu :)

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

4 Answers

Maria Terence Nov 13, 2016 at 04:37 AM
0

Hi Ashu,

I dont think you can achieve using Single Cycle Maintenance plans, you need to use Maintenance Strategy and assign packages to Operations.

In your case, Operation 1, Operation 2, Operation 3, should be under one package, then Operation 3 and Operation 4 should be under one package

Regards

Terence

Share
10 |10000 characters needed characters left characters exceeded
Peter Atkin Nov 15, 2016 at 07:18 AM
0
Share
10 |10000 characters needed characters left characters exceeded
Ashu Aggarwal Nov 15, 2016 at 08:08 AM
0

Hi,

But how operation are selected while generating order , it work on cycle provided (either performance or time based in cycle sets)

could you please share some example or any link further.

Thanks

Ashu :)

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Ashu,

Create a strategy with two packages:

  • Package 1 - 15 days (hierarchy level 1)
  • Package 2 - 30 days (hierarchy level 2)

Create your task list and assign OP1/2/3 to package 1, and OP4 to package 2.

Create a plan and schedule.

PeteA

0
Jesus Rene Vega Nov 15, 2016 at 04:12 PM
0

Hi Ashu Aggarwal

When you create the task list, in operation section, asign one package for all:

1.-select the button "MntPack"

2.-Asign the strategy to the operations

3.- Create a plan

4.- schedule the plan.

Remember create your strategy IP11