Hi!
We have implemented HR, MM,FICO,PS,SD modules. Now, there is a requirement to create BOM. I hope unless PP is implemented BOM can not be integrated fully with PS or other modules. In the production it wont allow us to create BOM by CS01. Am I correct? Please give your suggestions or inputs.
Bekele
Hi,
If you have to do the material requirement planning for your projects then you can create material bom through CS01 transaction code.
Also you can create WBS BOM through CS71 (single level) & CS74 (multilevel) transaction codes.
refer below link on bom use in ps,
https://forums.sdn.sap.com/click.jspa?searchID=26348099&messageID=6708945
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
OK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think some clarity is required.
WBS element is sort of cost center/collector, Network order is just like production order and activities can be trated as operations (but in activities cost also can be captured).
IF the intension is to make semifinish material from components then there are 2 ways.
1. Create production usageBOM, create production order with A/c assignment WBS element and confirm the production order
2. Create BOM,Copy the bom to WBS through cn33 and ref point, then with that ref. consume the components to network order and make the Semifinish material with +/- sign.
PRoduction order is created in a controlled environment and Network order is used in case of uncontrolled environment eg. customer site.
Hope This clarifies your issue
Sameer Wad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
PP should be there, if you are creating BOM & running MRP.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you want to produce material (In House Production) then you need Production Planning Implemented.From Project we are only responsible for material Request to PP.Please discuss with your PM about this requirement.
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.