I am using Milestones for Milestone Trend analysis.. I want the milestone to get automatically confirmed with the actual date when I confirm the activity. When i confirm the activity, I maintained that system proposes for Milestone date confirmation and the moment I enter the date, it changes the scheduled date also and the graph is incorrect. Why the scheduled date is getting changed ? Where I am making mistake ?

Thanks in advance,

Vinodh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

to transfer the dates to the milestone, ensure that Milestone automatic is ticked in confirmation parameters (OPST). check your scheduling paramters (OPU6) and in adjust dates field, try to set it to "do not adjust basic dates"

rgds.

Former Member
0 Kudos

Hi Ramesh,

Infact, I have maintained these two settings already and even after that I am facing this problem. But in OPU6, I had flagged the "Automatic Scheduling" also. I think this should not be a problem as this is for Scheduling at the time of saving..

Regards,

Vinodh