on 05-16-2009 1:36 PM
Hi,
I am using Milestones for Milestone Trend analysis.. I want the milestone to get automatically confirmed with the actual date when I confirm the activity. When i confirm the activity, I maintained that system proposes for Milestone date confirmation and the moment I enter the date, it changes the scheduled date also and the graph is incorrect. Why the scheduled date is getting changed ? Where I am making mistake ?
Thanks in advance,
Vinodh
hi,
to transfer the dates to the milestone, ensure that Milestone automatic is ticked in confirmation parameters (OPST). check your scheduling paramters (OPU6) and in adjust dates field, try to set it to "do not adjust basic dates"
rgds.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.