Skip to Content
0
Former Member
May 16, 2009 at 12:36 PM

Problem with MTA

30 Views

Hi,

I am using Milestones for Milestone Trend analysis.. I want the milestone to get automatically confirmed with the actual date when I confirm the activity. When i confirm the activity, I maintained that system proposes for Milestone date confirmation and the moment I enter the date, it changes the scheduled date also and the graph is incorrect. Why the scheduled date is getting changed ? Where I am making mistake ?

Thanks in advance,

Vinodh