Hi Experts,
We got an error "Error in commitment check(see costing log message no:CO634)" when creating the maintenance order for cosuming the non stock material or using the external contractors for the work. Generally it is throwing error when we try to create purchase requistion thru maintenance order.
We have budget implemented in our project and even we have unblocked the activity available control for this but still getting the same error. We also posted money into the cost center and tested the maintenace order still we are getting same error. We tried creating teh purch. req directly thru ME51N now we can able to create it, the problem is only when we try to create purch. req. thru order we are getting the error.
We couldn't figure out why it is stopping us. Could anyone please let us knwo what seetings we need to do allow work orders without validating for the budget. Your help will be really aprreciated.
I can send you the screen shot of commitment settings and activitity available control in case anyone want to look at it. Thanks in advance.
Regards,
Praveen Kumar