SRM 4.0 approval through email

11 Views

Hi Experts,

I have a requirement where I have to recalculate the delivery date when it is approved through email and through SRM portal in SRM4.0.

I am using the BADI "BBP_DOC_CHANGE_BADI", in that I have mentioned sy-tcode = 'BBPWI' or 'BBPSC07' and written the logic for recalculation but the recalculation of delivery date is not happening WHEN IT IS APPROVED through Email and working fine when approved through portal.

Please let me know what more needs to be done?

Thanks ,

P.Bharadwaj.